New timelapse footage shows the latest developements in the project to replace a bridge fro the 1930s over the River Soar.
Work on the £19.5m Zouch Bridge replacement has reached a key milestone with the successful ‘launch’ of steel beams across the River Soar.
Engineers winched the beams 36 metres into place using a specialist jacking system, avoiding the need for cranes due to nearby high-voltage cables.
Leicestershire County Council is replacing the deteriorating existing bridge on the A6006, a key trade and transport route linking Hathern and Zouch on the Leics / Notts border.
The new bridge is being built by specialist contractors Eric Wright Civil Engineering. The launch of the steels is the second to take place – the first happened in August.
Councillor Charles Whitford, Leicestershire County Council cabinet member for highways and transport, said: “I had the opportunity to visit the site recently and it’s been fascinating to understand how this bridge is being constructed.
“The presence of the overhead wires means the steels cannot just be craned in so they have to be launched, essentially carefully shunted, into place. It’s a complex procedure that requires a lot of precision and care.
“The A6006 is a key route that includes links to the airport and Freeport developments so we have done our best to keep disruption to a minimum and build the new bridge alongside the old one, rather than in the same place.
“We’d like to thank everyone for bearing with us while we complete this scheme.”
A447 still closed after burst water pipe
Unwanted bikes needed to give to Leicestershire’s young people a chance to learn to cycle
11-year-old injured after collision in Stoney Stanton
£1K reward to help find wanted man with links to Nuneaton
Body found in search for missing 85-year-old
Appeal for young person who spoke to missing Glenda to come forward
Britain’s most-bashed bridge is in Hinckley
Missing 85-year-old seen on CCTV in Hinckley